Project description:

 

Subsea
7 is the EPRD contractor of the Markham ST-1 platform removal project. Seaway 7
scope consists of engineering, hook-down, removal and transportation to
dismantling yard of platform structures.

 

ARC’s scope of work:

Seaway 7 requested ARC to support them with the engineering works for platform
removal. Following tasks have been performed:

Structural Verification of Jacket Integrity during cutting, lifting and transportation

Engineering checks of various reports

Perform Project Engineering tasks like subcontractor coordination, mobilization support, equipment lists, preparing manuals

Offshore support – Field Engineering during execution on board HLV

 