Boskalis Subsea Cables – Sandbank & Hornsrev 3 (HR3) Offshore Wind Farms – Engineering support (office & offshore) CPS stabilization via rock bag installation

Project description:

Boskalis was awarded the stabilisation of the Cable Protection System (CPS) installed on the infield cables exiting the monopiles of the Sandbank & Hornsrev 3 (HR3) Offshore Wind Farms.

ARC’s scope of work:

Boskalis Subsea Cables subcontracted ARC’s for the following tasks:

  •Site visit for rock bag mock-up/test lift at rock bag manufacturer premises.
   •Office-based engineering support including delivery of rock bags installation procedure / method statement, deck layouts etc. and liaison with the Client (Vattenfall).

     •Offshore Field Engineering support on board the Offshore Support Vessel (OSV) North Sea Giant from late February – late April. Concluded by closeout work.