Boulder Clearance Tool

Project description:

Arkona wind farm site is located approx. 35 km northeast of the island of Rügen within the Exclusive Economic Zone of the Federal Republic of Germany.

There will be 60 WTGs of 6MW each resulting in 385MW total capacity.

 

ARC’s scope of work:

VBMS has contracted ARC to perform the following Design and Engineering support:

T-Rex boulder clearance tool; Tool Mobilization, Launch,  Normal operations, Recovery and Maintenance procedures
Operational support assigning a Field Engineer for the boulder clearance execution phase