Nordsee Ost - Installation Engineering

RWE Innogy GmbH contracted Visser & Smit Marine Contractors GmbH for the installation of the inter-array cables within the Nordsee Ost offshore wind farm.
Nordsee Ost offshore wind farm is located about 30 kms North/North-West of the island of Helgoland in the North of Germany. The site will consist of 48 6.15MW wind turbines and an offshore substation in water depths between approximately 22 and 26 meters.

ARC’s scope of work:
VSMC contracted ARC to make a conceptual design of the cable pull-in frame, which will be used for the infield cable pull-ins at the offshore substation. The designed frame comprises 3 sections connected by bolted flange connections.