Buoy and Clump Weight Design

Project description:

Oranje-Nassau Energie has approached Glomar for the installation of a mooring buoy, clump weight, required lines and rigging for a permanently located ERRV offshore mooring system to anchor an Emergency Response and Rescue Vessel (ERRV) outside the 500m safety zone of the Sean PAPA.

 

ARC’s scope of work:

Glomar Subsea assigned ARC & Auxilium Offshore to perform the design and installation engineering for the buoy, clumpweight and associated chains in the SEAN P field.

Clump and chain design

– Installation / overboarding procedures

– Mobilization Manual & Execution Plan

– Procurement of clumpweight, chain, installation aids, etc.